HBC Offshore Solutions Ltd have recommenced the operations supporting Fugro with the installation of the array cables on the Rampion Offshore Wind Farm project.
Fugro is laying and bury 122 array cables with its construction and installation vessels Fugro Symphony and Fugro Saltire and using one of its two Q1400 trenching systems to bury the cables. HBC Offshore Solutions Ltd will provide the rigging teams and cable installation equipment supporting Fugro during the installation of the cables at both the WTG’s and the offshore Substation.
The Rampion Offshore Wind Farm being built by E.ON, the Green Investment Bank plc and Canadian energy company Enbridge, will consist of 116 turbines, each with a generating capacity of 3.45 MW. Construction is expected to be completed in 2018.